BP introduced that, along with its companion the Oman Oil Company Exploration & Production, it has authorized the event of Ghazeer, the second part of the large Khazzan gasoline subject in Oman.
The remaining funding determination (FID) for Ghazeer follows the profitable start-up of Khazzan’s first part of improvement in September 2017. This mission, which began manufacturing forward of schedule and below finances, is now producing at design capability of round 1 billion cubic toes of gasoline a day (bcf/d) and round 35,000 barrels a day of condensate.
Yousuf Al Ojaili, President of BP Oman mentioned: “Following the profitable startup of Khazzan, we’re happy to announce the sanction of Ghazeer, BP’s first mission FID of 2018. Through the switch of industry-leading abilities and know-how from BP’s world portfolio, we look ahead to futher creating this gasoline subject that’s anticipated to help Oman’s power wants for a lot of a long time to come back.”
The Ghazeer mission is anticipated to come back onstream in 2021 and ship an extra zero.5 bcf/d and over 15,000 bpd condensate manufacturing. Drilling on the primary three improvement wells has begun, following appraisal drilling on Ghazeer final 12 months. Initial building work has already began at Khazzan to accommodate a 3rd gasoline prepare and related infrastructure.
The Khazzan and Ghazeer, developments are anticipated to ship whole manufacturing of 10.5 tcf of gasoline and round 350 million barrels of condensate by way of the top of concession.
BP is the operator of Block 61 and holds a 60% curiosity. The Oman Oil Company Exploration & Production holds a 40% curiosity. (Source: BP = Image: Woeker in Khazzan subject/Argaam)

The publish KHAZZAN GAS FIELD: DEVELOPMENT OF GHAZZER APPROVED appeared first on Energy Global News.

Read more at Source link